As-Built and O&M Transmittal Summary

An As-Built and O&M Transmittal Summary is attached to as-built drawings and operation and maintenance manuals submitted by the Construction Manager on projects having multiple bid packs.

Original Form

Who originates it?:
Project Manager
Location:
click here
Notes:
This form is available for PDC staff to access in Meridian Forms, and use as a template for a new project.

Final Document Placement

Who is responsible?:
Project Manager
Location:
Unifier Business Process
Notes:
The Summary will be attached in the final Payment Application process.

 

Detailed Workflow

Before or at Substantial Completion, the Construction Manager will submit As-Built Drawings and O&M Documents to the Project Manager.  The Project Manager will fill out the As-Built and O&M Transmittal Summary and forward the set of as-builts with transmittal to the Records Manager. The O&M documents will be transmitted electronically using the Unifier Submittals process. The documents will go through the Facilities Information Services Manager, then the original Summary will be returned to the Project Manager, who will then scan and attach to the final Payment Application.