Final Commissioning Report

Contains data from the commissioning work performed on a project. 

Original Document

Who originates it?:
Other
Notes:
The MSU Commissioning department will create the Report.

Final Document Placement

Who is responsible?:
Lead Designer
Location:
Unifier Document Manager
Notes:
Move the Report from the "TRANSMITTALS TO BE FILED" folder to the "PHYSICAL PLANT SERVICES" folder.

 

Detailed Workflow

The MSU Commissioning department will create the Final Commissioning Report and send it to the Lead Designer for review, using the Transmittal process in Unifier.  The Lead Designer may return the Report to the Commissioning department for revision, or will file the report in the appropriate folder in the Unifier Document Manager.