Project Rating by Contractor

The Contractor is required to rate all aspects of the project, and submit the Project Rating by Contractor form in Unifier as part of the close-out documentation. 

Original Document

Who originates it?:
Construction Manager,General Contractor
Notes:
A "PROJECT RATING BY CONTRACTOR" form is in Skire.

Final Document Placement

Who is responsible?:
Construction Manager,General Contractor
Location:
Unifier Business Process
Notes:
General Contractor or Construction Manager fills out a "PROJECT RATING BY CONTRACTOR" form in Unifier.

 

Detailed Workflow

The Skire form is automatically created for each Capital Project, and is assigned as a task in Skire for the Contractor.  The Contractor will fill out the form at the end of the construction phase.  The Project Rating form will go through a review process by the Project Representative, Lead Designer, Director of EAS and Contract Administrator.  The form can be found in the Unifier project by navigating to the Logs - Miscellaneous - Score Cards folder.