Schedule of Submittals

The Schedule of Submittals (or Submittal Log) is a list of all the project submittals required from the Contractor.

Original Document

Who originates it?:
General Contractor
Notes:
The Contractor may use their own format for the Schedule of Submittals.

Final Document Placement

Who is responsible?:
General Contractor
Location:
Unifier Business Process
Notes:
Schedule of Submittals is attached in the Submittals process.

 

Detailed Workflow

The construction documents, specifically the technical specifications, require the Contractor to submit product data, samples and shop drawings to the architect and engineer for approval.  The Schedule of Submittals (or Submittal Log) is a list of all the required submittals from the Contractor for the project.  The Contractor will submit a Schedule of Submittals using the Unifier Submittals process.  The Project Representative will review the Schedule of Submittals and may request revisions from the Contractor.  The Contractor will receive  a notification in Unifier when it is approved.