Skip to main content
 

Surveyor's Log and Certificate

A submittal required from the Contractor on projects involving a new building or major addition.

Original Document

Who originates it?:
General Contractor

Final Document Placement

Who is responsible?:
General Contractor
Location:
Unifier Business Process
Notes:
Attach to the Transmittals process. Project Representative will move the document from the "TRANSMITTALS TO BE FILED" folder to the "SITE WORK" folder.

 

Detailed Workflow

The Contractor will submit the Surveyor's Log and Certificate using the Transmittal process.  The Project Representative will review the submittal and may return it to the Contractor for revision.  The Contractor will be notified in Unifier  when the docuemnt is approved.  The Project Representative will file the final document.