Tests

Various tests may be required as submittals from the Contractor at project close-out.  Examples are as follows: Asphalt, Bacteriological for Water Mains, Concrete, Hydrostatic Pressure for Water Mains, PCB, Sanitary Sewer Low-Pressure Air, Soil Testing Reports, Steam Pipe Weld Maps, Steam/Condensate Pipe Leak Test Report, and Subgrade-Subbase Density Test Reports.

Original Document

Who originates it?:
General Contractor

Final Document Placement

Who is responsible?:
General Contractor
Location:
Unifier Business Process
Notes:
Tests are attached in the Submittals process.

 

Detailed Workflow

At the construction close-out of a project, the Contractor will submit any required Test reports, using the Submittals process.  The Project Representative will review the Tests and may request revisions from the Contractor.  The Contractor will receive notification in Unifier when the Tests are approved.