Skip to main content
 

Utility Meter Installation Request

Form required by the MSU Power and Water Department for new utility meters (electric, water, steam and condensate).

Original Form

Who originates it?:
Project Manager
Location:
click here
Notes:
This form is available for IPF Staff to access in Meridian Forms, and use as a template for a new project.

Final Document Placement

Who is responsible?:
Project Manager
Location:
Unifier Document Manager
Notes:
Upload into the "PHYSICAL PLANT SERVICES" folder.

 

Detailed Workflow

Early in the construction phase, the Project Manager will fill out the Utility Meter Installation Request form for each new utility meter required on a project.  The form will be given to Rick Johnson at the MSU Power and Water Department who will purchase and arrange for delivery of the meter(s).  The person who fills out the form will file it in the Unifier Document Manager for the project.